Start of the construction

Construction has started of a greenfield compound feed factory just outside of Abidjan in the new industrial zone of PK in Attingue’ with an initial capacity of 100.000 MT pa. This factory will produce high quality complete feed, which will expand the current portfolio of Koudijs concentrates and specialty feeds. Production is planned to commence during the second half of 2022.



February 2022: Impressive landmarking

First part of the production tower is being erected, the building is becoming an impressive landmarking at the industrial zone.


October 2021: Construction work

On-site we are working on the foundations of the warehouse and production building. Below you can see the formwork for the foundation of the production tower.


September 2021: Start ground work

Work was carried out on the foundation of the warehouse and the production building on site. All leveling work is ready as well as the fencing with the exception of placing the barbed wire.


Start of the construction

On the 10th of September 2021 we had the honour and pleasure to lay the first stone of the greenfield feed mill in Ivory Coast. The event was attended by 350 guest of which the ambassador of the Netherlands, the Ivorian minister of animal resources and other local government official that assisted us in achieving our goals so far.